  • WwTW update
  • WwTW update
  • WwTW update
WwTW update

Second-generation modular design, installed and ready to connect in less than 4 hours

  • £170,000 Contract value
  • 7 monthsProject duration
  • 8 metresLV assemblies
  • MCC1 No
  • WwTW upgrade with DfMA delivery
  • WwTW upgrade with DfMA delivery
  • WwTW upgrade with DfMA delivery
WwTW upgrade with DfMA delivery

Replacement MCC delivered as a packaged plant-room including kiosk, sub-frame and electrical fit out

  • £180 kContract value
  • 28 weeksProject duration
  • 6 metresLV assemblies
  • MCC1 No
  • IntegrationPLC HMI
  • WwTW upgrade utilising DfMA plant
  • WwTW upgrade utilising DfMA plant
  • WwTW upgrade utilising DfMA plant
WwTW upgrade utilising DfMA plant

Supply of MCC packaged plantroom including electrical fit out fibre optic and radio comms systems

  • £130 kContract value
  • 24 weeksProject duration
  • 7.5 metresLV assemblies
  • MCC1 No
  • IntegrationHMI